List of Active and Planned Projects

Company
Name

Project
Description

Project
Location

Cost in
Millions

Construction
Schedule

Remarks

Albian Sands Energy Inc.

'Jackpine' Mine -- Mining and Extraction Facility phase 1

RM of Wood Buffalo (near Fort MacKay)

$2000.0


Proposed. Approved Feb 04. Phase 1 will follow Muskeg R and Scotford expansions. Includes 170MW power plant

Albian Sands Energy Inc.

Muskeg River Mine Expansion

RM of Wood Buffalo

$2500.0


Proposed for 2006 - 2009. Application filed April 2005.

BA Energy Inc.

'Alberta Heartland' Bitumen Upgrader Phase 1

Strathcona County (NW of Bruderheim)

$ 900.0

2005-2008

Under construction. Jacobs Canada / Larsen & Toubro. Approved July 2005.

BA Energy Inc.

'Alberta Heartland' Bitumen Upgrader Phases 2 and 3

Strathcona County

$2000.0


Proposed once phase 1 is completed

BlackRock Ventures Inc.

'Orion' Heavy Oil SAGD Facility (Phases 1 and 2)

MD of Bonnyville (Hilda Lake)

$ 340.0

2005-2010

Under construction. Approved Oct 2004. Phased development, building to 20,000 bpd.

Canadian Natural Resources Ltd.

'Primrose North' Cyclic Steam Stimulation (CSS) Project

Lakeland County (Primrose / Wolf Lakes)

$ 250.0

2004-2007

Under construction

Canadian Natural Resources Ltd. (CNRL)

'Project Horizon' Mining and Drilling Project phase 2

RM of Wood Buffalo

$1700.0


Proposed for 2006 - 2009. Approved Jan 2004.

Canadian Natural Resources Ltd. (CNRL)

'Primrose East' Cyclic Steam Stimulation (CSS) Project

Lakeland County

$ 600.0


Proposed for 2007 - 2008. Includes 85MW cogen plant. Application filed.

Canadian Natural Resources Ltd. (CNRL)

'Project Horizon' Mining and Drilling Project phase 3

RM of Wood Buffalo

$1400.0


Proposed for 2009 - 2012. Approved Jan 2004.

Canadian Natural Resources Ltd. (CNRL)

'Project Horizon' Mining and Drilling Project phase 1

RM of Wood Buffalo

$6800.0

2005-2008

Under construction. SNC-Lavalin / Snamprogetti Canada Inc. EPC Froth Teatment Plant SNC-Lavalin.

Connacher Oil and Gas

''Great Divide' SAGD Pilot Plant

RM of Wood Buffalo (SW of Fort McMurray)

$ 150.0


Proposed for 2006

ConocoPhillips Canada / TotalFinaElf / Devon Energy

'Surmont' SAGD Bitumen Commercial Project

RM of Wood Buffalo (near Anzac)

$1400.0

2004-2013

Under construction. Phase 1 (2004-2006).

Devon Canada Corp.

'Jackfish' SAGD Oilsands Project Phase 2 (J2)

RM of Wood Buffalo (SE of Conklin)

$ 500.0


Proposed for 2008 - 2009. Planned facility construction start third quarter 2008. Decision mid-2006.

Devon Canada Corp.

'Jackfish' SAGD Oilsands Project Phase 1

RM of Wood Buffalo (SE of Conklin)

$ 450.0

2005-2007

Under construction. Approved Dec 2004.

EnCana Corporation

Foster Creek Commercial Thermal Recovery Project Phase 3

Lakeland County (Foster Creek)

$ 844.0


Proposed construction start 2007. Applications filed May 02.

EnCana Corporation

Foster Creek Commercial Thermal Recovery Project phase 2

Lakeland County (Foster Creek)

$ 440.0


Proposed. Applications filed. Will include 80MW co-gen plant.

EnCana Corporation

SAGD Bitumen Production

RM of Wood Buffalo (Christina Lake)

$ 575.0

2000-2009

Under construction. AMEC / Titan Projects JV(EP & CM). Three phases. Planned construction phase 3 2007 - 2009.

Husky Energy Inc.

'Sunrise Thermal Project' Phase 2

RM of Wood Buffalo

$1900.0


Proposed for 2012 - 2014.

Husky Energy Inc.

Heavy Oil Upgrader Expansion

Lloydminster

$2300.0


Proposed. Detailed engineering work to start.

Husky Energy Inc.

'Sunrise Thermal Project' SAGD Oilsands Project Phase 1 (Kearl Lease 187)

RM of Wood Buffalo (N of Fort McMurray)

$ 800.0


Proposed for completion by 2012. Application approved. Corporate approval by end 2006.

Husky Energy Inc.

'Tucker Lake' SAGD Project

MD of Bonnyville (NW of Cold Lake)

$ 500.0

2005-2006

Nearing completion. Approved July 2004. Nordic Acres Engineering (FEED). SNC-Lavalin / PCL Industrial Management (Central Plant).

Imperial Oil Limited

Extension of Phases 9 & 10 'Mahihkan North'

MD of Bonnyville

$ 350.0

2005-2006

Under construction. Approved Feb 2004.

Imperial Oil Resources

Heavy Oil Plant Expansion Phases 14 to 16 'Nabiye'

MD of Bonnyville (north of Marie Lake)

$ 650.0


Proposed. Includes wells, field facilities and a plant to generate steam, process bitumen and treat water. Approved Feb 2004.

Imperial Oil Resources / ExxonMobil Canada

'Kearl Lake' Oilsands Mine (Kearl Lease 187) Phase 1

RM of Wood Buffalo

$2300.0


Proposed for 2007 - 2010, pending approvals. Three production trains / phases of development in total. Application filed for regulatory approval for all three phases.

Japan Canada Oil Sands Limited (JACOS)

Hangingstone SAGD Commercial Production Project

RM of Wood Buffalo (S of Fort McMurray)

$ 450.0


Proposed. Two phases. Planned construction start 2006.

North West Upgrading Inc.

Bitumen Upgrader Phases 2 and 3

Sturgeon County (near Redwater)

$3200.0


Proposed for 2010 to 2015. Application filed January 2006.

North West Upgrading Inc.

Bitumen Upgrader Phase 1

Sturgeon County

$1600.0

2007-2009

Announced. Pending approvals expected by early 2007. Application filed January 2005.

OPTI Canada / Nexen Inc.

'Long Lake' Water Treatment and Steam Generation Facility Expansion

RM of Wood Buffalo

$ 250.0


Proposed

OPTI Canada / Nexen Inc.

'Long Lake' SAGD Project Phase 2 (Kinosis)

RM of Wood Buffalo

$2790.0


Proposed for 2008 - 2010. Cost estimates are preliminary.

OPTI Canada Inc. / Nexen Inc.

'Long Lake' SAGD Heavy Oil Project Phase 1

RM of Wood Buffalo (near Anzac)

$3840.0

2004-2007

Under construction. Flint Infrastructures Ltd., Ledcor Projects Inc., Colt Engineering, Fluor. Approved Aug 2003. Upgrader, co-gen facility (370MW) and upgrader capacity.

Petro-Canada / UTS Energy / Teck Cominco

'Fort Hills' SAGD Project Stage 2

RM of Wood Buffalo

$1300.0


Proposed

Petro-Canada / UTS Energy Corp. / Teck Cominco

'Fort Hills' Oilsands Project

RM of Wood Buffalo

$2000.0


Proposed for 2006 - 2010. Planned construction start mid - 2006, production start in 2011.

Petro-Canada Oil and Gas

Strathcona Refinery Conversion to Upgrade Bitumen

Strathcona County

$1600.0

2004-2008

Under construction. Approved.

Petro-Canada Oil and Gas

MacKay River SAGD Expansion

RM of Wood Buffalo (NW of Fort McMurray)

$ 810.0


Proposed. Application filed Dec 05.

Petro-Canada Oil and Gas / Nexen Inc.

'Meadow Creek' SAGD Bitumen Production

RM of Wood Buffalo (S of Ft McMurray)

$ 800.0


Proposed. Application under review. Project includes 330MW co-gen plant.

Shell Canada

Scotford Upgrader Expansion (De-bottleneck and Addition of Third Bitumen Processing Train)

Strathcona County (Scotford)

$2700.0

2006-2010

Announced. Application filed April 2005. Public hearing Dow Centre on June 26.

Suncor Energy Inc.

New Bitumen Production Facilities at 'Firebag' Site

RM of Wood Buffalo

$1000.0


Proposed for 2005 - 2007. Approved Mar 2004.

Suncor Energy Inc.

Upgrader Expansion

RM of Wood Buffalo

$2100.0


Proposed for 2006 - 2008. Approved Mar 2004. Corporate approval announced.

Suncor Energy Inc.

Petroleum Coke Gasifier for 'Voyageur' Upgrader

RM of Wood Buffalo

$ 600.0


Proposed. Included with application for Voyageur upgrader March 2005. Cost estimate preliminary.

Suncor Energy Inc.

Steepbank Mine Extension

RM of Wood Buffalo

$ 350.0


Proposed for 2007 - 2010. Application filed.

Suncor Energy Inc.

'Voyageur' Oil Sands Facility Expansion (Third Oil Sands Upgrader)

RM of Wood Buffalo

$5900.0


Proposed for 2007 - 2010. Applications filed March 2005. Preliminary cost estimate. Project does not include bitumen feed to upgrader.

Syncrude Canada Ltd.

Continuous Improvement

RM of Wood Buffalo (Fort McMurray)

$1500.0

1997-2007

Underway

Syncrude Canada Ltd.

Phase 4: Upgrader Expansion Phase 2 / Aurora Mine Train 3

RM of Wood Buffalo (Fort McMurray)

$2300.0


Proposed. Pre-engineering study underway (AMEC). Expansion SNC-Lavalin, Fluor Daniel. Train 3 AMEC.

Syncrude Canada Ltd.

Sulphur Emission Reduction Program (SERP)

RM of Wood Buffalo (Mildred Lake)

$ 400.0


Proposed for 2005 - 2009. Application approved.

SynEnCo Energy Inc. / SinoCanada Petroleum Corp.

'Northern Lights' Bitumen Upgrader

Sturgeon County

$3600.0


Proposed for 2008 - 2010. Application to be filed late 2006.

SynEnCo Energy Inc. / SinoCanada Petroleum Corp.

'Northern Lights' Oilsands Mine and Extraction Plant phases 1 and 2

RM of Wood Buffalo

$2500.0


Proposed for 2008 - 2010. Application to be filed by mid-2006. Colt/AMEC.

Total Canada Ltd.

'Joslyn Creek' SAGD Project Phase 3 and North Mine Development

RM of Wood Buffalo

$1500.0


Proposed construction start Phase 3 in 2007, mine in 2008. Application for phase 3A filed. Application for mine filed early 2006.

Total Canada Ltd.

Bitumen Upgrader

Strathcona County or Wood Buffalo

$5000.0


Proposed. $US. Decision by mid-2006. Upgrader to be built by 2014.