Company
Name |
Project
Description |
Project
Location |
Cost in
Millions |
Construction
Schedule |
Remarks |
Albian Sands Energy Inc. |
'Jackpine' Mine -- Mining and Extraction Facility phase 1 |
RM of Wood Buffalo (near Fort MacKay) |
$2000.0 |
|
Proposed. Approved Feb 04. Phase 1 will follow Muskeg R and Scotford expansions. Includes 170MW power plant |
Albian Sands Energy Inc. |
Muskeg River Mine Expansion |
RM of Wood Buffalo |
$2500.0 |
|
Proposed for 2006 - 2009. Application filed April 2005. |
BA Energy Inc. |
'Alberta Heartland' Bitumen Upgrader Phase 1 |
Strathcona County (NW of Bruderheim) |
$ 900.0 |
2005-2008 |
Under construction. Jacobs Canada / Larsen & Toubro. Approved July 2005. |
BA Energy Inc. |
'Alberta Heartland' Bitumen Upgrader Phases 2 and 3 |
Strathcona County |
$2000.0 |
|
Proposed once phase 1 is completed |
BlackRock Ventures Inc. |
'Orion' Heavy Oil SAGD Facility (Phases 1 and 2) |
MD of Bonnyville (Hilda Lake) |
$ 340.0 |
2005-2010 |
Under construction. Approved Oct 2004. Phased development, building to 20,000 bpd. |
Canadian Natural Resources Ltd. |
'Primrose North' Cyclic Steam Stimulation (CSS) Project |
Lakeland County (Primrose / Wolf Lakes) |
$ 250.0 |
2004-2007 |
Under construction |
Canadian Natural Resources Ltd. (CNRL) |
'Project Horizon' Mining and Drilling Project phase 2 |
RM of Wood Buffalo |
$1700.0 |
|
Proposed for 2006 - 2009. Approved Jan 2004. |
Canadian Natural Resources Ltd. (CNRL) |
'Primrose East' Cyclic Steam Stimulation (CSS) Project |
Lakeland County |
$ 600.0 |
|
Proposed for 2007 - 2008. Includes 85MW cogen plant. Application filed. |
Canadian Natural Resources Ltd. (CNRL) |
'Project Horizon' Mining and Drilling Project phase 3 |
RM of Wood Buffalo |
$1400.0 |
|
Proposed for 2009 - 2012. Approved Jan 2004. |
Canadian Natural Resources Ltd. (CNRL) |
'Project Horizon' Mining and Drilling Project phase 1 |
RM of Wood Buffalo |
$6800.0 |
2005-2008 |
Under construction. SNC-Lavalin / Snamprogetti Canada Inc. EPC Froth Teatment Plant SNC-Lavalin. |
Connacher Oil and Gas |
''Great Divide' SAGD Pilot Plant |
RM of Wood Buffalo (SW of Fort McMurray) |
$ 150.0 |
|
Proposed for 2006 |
ConocoPhillips Canada / TotalFinaElf / Devon Energy |
'Surmont' SAGD Bitumen Commercial Project |
RM of Wood Buffalo (near Anzac) |
$1400.0 |
2004-2013 |
Under construction. Phase 1 (2004-2006). |
Devon Canada Corp. |
'Jackfish' SAGD Oilsands Project Phase 2 (J2) |
RM of Wood Buffalo (SE of Conklin) |
$ 500.0 |
|
Proposed for 2008 - 2009. Planned facility construction start third quarter 2008. Decision mid-2006. |
Devon Canada Corp. |
'Jackfish' SAGD Oilsands Project Phase 1 |
RM of Wood Buffalo (SE of Conklin) |
$ 450.0 |
2005-2007 |
Under construction. Approved Dec 2004. |
EnCana Corporation |
Foster Creek Commercial Thermal Recovery Project Phase 3 |
Lakeland County (Foster Creek) |
$ 844.0 |
|
Proposed construction start 2007. Applications filed May 02. |
EnCana Corporation |
Foster Creek Commercial Thermal Recovery Project phase 2 |
Lakeland County (Foster Creek) |
$ 440.0 |
|
Proposed. Applications filed. Will include 80MW co-gen plant. |
EnCana Corporation |
SAGD Bitumen Production |
RM of Wood Buffalo (Christina Lake) |
$ 575.0 |
2000-2009 |
Under construction. AMEC / Titan Projects JV(EP & CM). Three phases. Planned construction phase 3 2007 - 2009. |
Husky Energy Inc. |
'Sunrise Thermal Project' Phase 2 |
RM of Wood Buffalo |
$1900.0 |
|
Proposed for 2012 - 2014. |
Husky Energy Inc. |
Heavy Oil Upgrader Expansion |
Lloydminster |
$2300.0 |
|
Proposed. Detailed engineering work to start. |
Husky Energy Inc. |
'Sunrise Thermal Project' SAGD Oilsands Project Phase 1 (Kearl Lease 187) |
RM of Wood Buffalo (N of Fort McMurray) |
$ 800.0 |
|
Proposed for completion by 2012. Application approved. Corporate approval by end 2006. |
Husky Energy Inc. |
'Tucker Lake' SAGD Project |
MD of Bonnyville (NW of Cold Lake) |
$ 500.0 |
2005-2006 |
Nearing completion. Approved July 2004. Nordic Acres Engineering (FEED). SNC-Lavalin / PCL Industrial Management (Central Plant). |
Imperial Oil Limited |
Extension of Phases 9 & 10 'Mahihkan North' |
MD of Bonnyville |
$ 350.0 |
2005-2006 |
Under construction. Approved Feb 2004. |
Imperial Oil Resources |
Heavy Oil Plant Expansion Phases 14 to 16 'Nabiye' |
MD of Bonnyville (north of Marie Lake) |
$ 650.0 |
|
Proposed. Includes wells, field facilities and a plant to generate steam, process bitumen and treat water. Approved Feb 2004. |
Imperial Oil Resources / ExxonMobil Canada |
'Kearl Lake' Oilsands Mine (Kearl Lease 187) Phase 1 |
RM of Wood Buffalo |
$2300.0 |
|
Proposed for 2007 - 2010, pending approvals. Three production trains / phases of development in total. Application filed for regulatory approval for all three phases. |
Japan Canada Oil Sands Limited (JACOS) |
Hangingstone SAGD Commercial Production Project |
RM of Wood Buffalo (S of Fort McMurray) |
$ 450.0 |
|
Proposed. Two phases. Planned construction start 2006. |
North West Upgrading Inc. |
Bitumen Upgrader Phases 2 and 3 |
Sturgeon County (near Redwater) |
$3200.0 |
|
Proposed for 2010 to 2015. Application filed January 2006. |
North West Upgrading Inc. |
Bitumen Upgrader Phase 1 |
Sturgeon County |
$1600.0 |
2007-2009 |
Announced. Pending approvals expected by early 2007. Application filed January 2005. |
OPTI Canada / Nexen Inc. |
'Long Lake' Water Treatment and Steam Generation Facility Expansion |
RM of Wood Buffalo |
$ 250.0 |
|
Proposed |
OPTI Canada / Nexen Inc. |
'Long Lake' SAGD Project Phase 2 (Kinosis) |
RM of Wood Buffalo |
$2790.0 |
|
Proposed for 2008 - 2010. Cost estimates are preliminary. |
OPTI Canada Inc. / Nexen Inc. |
'Long Lake' SAGD Heavy Oil Project Phase 1 |
RM of Wood Buffalo (near Anzac) |
$3840.0 |
2004-2007 |
Under construction. Flint Infrastructures Ltd., Ledcor Projects Inc., Colt Engineering, Fluor. Approved Aug 2003. Upgrader, co-gen facility (370MW) and upgrader capacity. |
Petro-Canada / UTS Energy / Teck Cominco |
'Fort Hills' SAGD Project Stage 2 |
RM of Wood Buffalo |
$1300.0 |
|
Proposed |
Petro-Canada / UTS Energy Corp. / Teck Cominco |
'Fort Hills' Oilsands Project |
RM of Wood Buffalo |
$2000.0 |
|
Proposed for 2006 - 2010. Planned construction start mid - 2006, production start in 2011. |
Petro-Canada Oil and Gas |
Strathcona Refinery Conversion to Upgrade Bitumen |
Strathcona County |
$1600.0 |
2004-2008 |
Under construction. Approved. |
Petro-Canada Oil and Gas |
MacKay River SAGD Expansion |
RM of Wood Buffalo (NW of Fort McMurray) |
$ 810.0 |
|
Proposed. Application filed Dec 05. |
Petro-Canada Oil and Gas / Nexen Inc. |
'Meadow Creek' SAGD Bitumen Production |
RM of Wood Buffalo (S of Ft McMurray) |
$ 800.0 |
|
Proposed. Application under review. Project includes 330MW co-gen plant. |
Shell Canada |
Scotford Upgrader Expansion (De-bottleneck and Addition of Third Bitumen Processing Train) |
Strathcona County (Scotford) |
$2700.0 |
2006-2010 |
Announced. Application filed April 2005. Public hearing Dow Centre on June 26. |
Suncor Energy Inc. |
New Bitumen Production Facilities at 'Firebag' Site |
RM of Wood Buffalo |
$1000.0 |
|
Proposed for 2005 - 2007. Approved Mar 2004. |
Suncor Energy Inc. |
Upgrader Expansion |
RM of Wood Buffalo |
$2100.0 |
|
Proposed for 2006 - 2008. Approved Mar 2004. Corporate approval announced. |
Suncor Energy Inc. |
Petroleum Coke Gasifier for 'Voyageur' Upgrader |
RM of Wood Buffalo |
$ 600.0 |
|
Proposed. Included with application for Voyageur upgrader March 2005. Cost estimate preliminary. |
Suncor Energy Inc. |
Steepbank Mine Extension |
RM of Wood Buffalo |
$ 350.0 |
|
Proposed for 2007 - 2010. Application filed. |
Suncor Energy Inc. |
'Voyageur' Oil Sands Facility Expansion (Third Oil Sands Upgrader) |
RM of Wood Buffalo |
$5900.0 |
|
Proposed for 2007 - 2010. Applications filed March 2005. Preliminary cost estimate. Project does not include bitumen feed to upgrader. |
Syncrude Canada Ltd. |
Continuous Improvement |
RM of Wood Buffalo (Fort McMurray) |
$1500.0 |
1997-2007 |
Underway |
Syncrude Canada Ltd. |
Phase 4: Upgrader Expansion Phase 2 / Aurora Mine Train 3 |
RM of Wood Buffalo (Fort McMurray) |
$2300.0 |
|
Proposed. Pre-engineering study underway (AMEC). Expansion SNC-Lavalin, Fluor Daniel. Train 3 AMEC. |
Syncrude Canada Ltd. |
Sulphur Emission Reduction Program (SERP) |
RM of Wood Buffalo (Mildred Lake) |
$ 400.0 |
|
Proposed for 2005 - 2009. Application approved. |
SynEnCo Energy Inc. / SinoCanada Petroleum Corp. |
'Northern Lights' Bitumen Upgrader |
Sturgeon County |
$3600.0 |
|
Proposed for 2008 - 2010. Application to be filed late 2006. |
SynEnCo Energy Inc. / SinoCanada Petroleum Corp. |
'Northern Lights' Oilsands Mine and Extraction Plant phases 1 and 2 |
RM of Wood Buffalo |
$2500.0 |
|
Proposed for 2008 - 2010. Application to be filed by mid-2006. Colt/AMEC. |
Total Canada Ltd. |
'Joslyn Creek' SAGD Project Phase 3 and North Mine Development |
RM of Wood Buffalo |
$1500.0 |
|
Proposed construction start Phase 3 in 2007, mine in 2008. Application for phase 3A filed. Application for mine filed early 2006. |
Total Canada Ltd. |
Bitumen Upgrader |
Strathcona County or Wood Buffalo |
$5000.0 |
|
Proposed. $US. Decision by mid-2006. Upgrader to be built by 2014. |